In early April we will meet Karl Hultman in Huddinge on one of our newly started projects. When we are on site, the project has been going on since mid-March and is scheduled to be completed in the fall of 2020. The work is about excavating about 1 mile with a total of 12 part stages, about 300 joints and about 70 low voltage cabinets.

– We all have indoormeetings through Skype but outdoor meetings on projects we run as usual. We keep our distance and greet each other without contact. It goes well, says Kalle.

At the moment we only have our subcontractor at site and they say that they use a variety of different aids to facilitate work such as lifting devices for cable and self-propelled asphalt saw. In addition, an SJA (Safe Job Analysis) is written according to Craftor’s SJA blocks and reconciliations are made every week with projectmanager Kalle.